Clemson Road BridgeStratagrid SG200 satisfied the structural requirements for the steepened soil slope. The bent, welded-wire form facing system accommodated both the concrete slope protection and vegetation. The reinforced slope eliminated the costly need for lengthening the bridge span or constructing a structural wall and provided the additional right-of-way required for the access road. StrataSlope gave SCDOT the best solution, making the project both structurally and economically sound. Learn More >> To download complete Case Study PDF, click on image on right.
Donzi LandfillThe design and construction of a Stratagrid-reinforced retaining structure around the existing Donzi landfill provided a safe, highly engineered method of expanding this tightly-restricted landfill. It was constructed with the landfill operator's own crews, and the completed project resulted in more than 3 million additional cubic yards of volume. Learn More >> To download complete Case Study PDF, click on image on right.
|